Building Permit Drawings in Ontario: Costs, Process & What You Need

Project in Orillia, ON by Max Humenyuk Design

Planning a home addition, renovation, deck, garage, secondary suite, duplex conversion or new home in Ontario?

Depending on the scope of work, you may need a building permit before construction can begin. A key part of the permit application is a complete set of building permit drawings showing what you intend to build and providing the technical information required for municipal review.

At Max Humenyuk Design, I prepare residential building permit drawings for homeowners, builders and contractors across Ontario, including Orillia, Barrie, Simcoe County, the Greater Toronto Area and surrounding communities.

This guide explains when you may need a permit, what drawings are typically required, how the process works and what to consider before starting your project.

What Projects Require a Building Permit in Ontario?

Building permits are commonly required when constructing a new building, adding to an existing building, making certain renovations or structural alterations, or changing the use of a building.

Common residential projects that may require permits include:

  • Home additions

  • Major renovations

  • Structural alterations

  • Custom homes

  • Secondary suites and additional dwelling units

  • Duplex and triplex conversions

  • Attached and detached garages

  • Decks and porches

  • Certain accessory structures

  • Basement renovations involving regulated work

  • Foundation work

  • Plumbing and HVAC alterations

Permit requirements can vary depending on the project and municipality.

Before starting construction, it is important to determine what approvals apply to your specific property and proposed work.

What Are Building Permit Drawings?

Building permit drawings are technical drawings prepared to communicate the proposed construction to the municipality.

They are more than a conceptual floor plan or rendering.

A proper permit drawing package needs to provide enough information for the proposed construction to be reviewed for compliance with applicable requirements and ultimately provide clear information about what is being built.

Depending on the project, the drawing package may include the following.

Site Plan

A site plan shows the property and where the proposed construction will be located.

It may include:

  • Property lines

  • Existing structures

  • Proposed construction

  • Building dimensions

  • Distances to property lines

  • Required setbacks

  • Other information necessary to demonstrate zoning compliance

Existing Floor Plans

For renovations, additions and conversions, existing floor plans may be required to document the current configuration of the building.

This establishes a clear distinction between what already exists and what is being proposed.

Proposed Floor Plans

Proposed floor plans typically show:

  • Room layouts

  • Walls

  • Doors and windows

  • Stairs

  • Dimensions

  • Structural elements

  • Plumbing fixtures where applicable

  • Other relevant construction information

Exterior Elevations

Exterior elevations show the proposed appearance and configuration of the building from the outside.

They can identify:

  • Building height

  • Windows and doors

  • Roof configuration

  • Exterior materials

  • Finished grades

  • Existing and proposed construction

Building Sections

Building sections cut vertically through the structure and help explain how the building is assembled.

Depending on the project, they may show foundations, floor systems, exterior walls, insulation, ceiling heights and roof construction.

Construction Details

Additional details may be required for specific building assemblies, connections or conditions that cannot be adequately communicated through the main drawings.

The exact requirements depend on the project and municipality.

Check Zoning Before You Design

One of the biggest mistakes homeowners can make is developing a complete design before determining what is actually permitted on the property.

The Ontario Building Code and municipal zoning by-laws serve different purposes.

A proposed addition, garage or other project could potentially satisfy Building Code requirements while failing to comply with the local zoning by-law.

Depending on the municipality and property, zoning requirements can regulate:

  • Front-yard setbacks

  • Rear-yard setbacks

  • Side-yard setbacks

  • Building height

  • Lot coverage

  • Parking

  • Building location

  • Permitted uses

  • Accessory structures

This is particularly important when planning an addition.

There may appear to be enough physical space on the property to build what you want, but the zoning regulations may limit the size or location of the proposed construction.

Checking these constraints early can prevent substantial redesign later.

How Does the Building Permit Process Work in Ontario?

Although individual municipal requirements vary, a typical residential project follows a similar process.

1. Review the Property and Project

The first step is understanding the existing property and what you want to build.

For an existing house, this may involve reviewing available documentation and measuring the existing building.

2. Investigate Zoning

The applicable municipal zoning requirements should be reviewed to determine whether the proposed project is feasible.

If the project does not comply with zoning, additional planning approvals may potentially be required before a building permit can be issued.

3. Develop the Design

Once the major property constraints are understood, the proposed design can be developed.

This can include decisions about:

  • Layout

  • Building size

  • Room configuration

  • Windows and doors

  • Roof design

  • Exterior appearance

  • Connections to the existing building

4. Prepare the Building Permit Drawings

The design is then developed into a coordinated technical drawing package.

The goal is to provide the municipality with the information required to review the proposed construction while also producing drawings that clearly communicate the project.

5. Coordinate Consultants

Depending on the project, additional professional services may be required.

These can potentially include:

  • Structural engineering

  • HVAC design

  • Surveying

  • Lot grading and drainage

  • Septic design

  • Other specialized consultants

Determining these requirements early can prevent delays when the permit package is ready for submission.

6. Submit the Building Permit Application

Building permit applications are generally submitted to the municipality responsible for Building Code enforcement in the area where the property is located.

The required drawings, forms, supporting documents and municipal fees are submitted as part of the application.

7. Respond to Permit Comments

The municipality reviews the application and may request revisions or additional information.

When comments are issued, the relevant drawings or documents are revised and resubmitted.

A complete and coordinated initial submission can reduce unnecessary rounds of review.

How Long Does a Building Permit Take in Ontario?

Permit timelines depend on the type of building and whether the application is complete.

For example, the prescribed review period for a complete permit application for a house is generally 10 business days.

However, that does not necessarily mean every residential project receives a permit exactly 10 days after submission.

Missing information, zoning issues, required approvals, engineering coordination or deficiencies identified during review can extend the overall timeline.

The most effective way to avoid unnecessary delays is to identify requirements early and submit a coordinated application.

How Much Do Building Permit Drawings Cost in Ontario?

There is no single price for building permit drawings because the amount of work required varies considerably.

A permit package for a relatively straightforward deck is very different from the drawings required for a large addition or custom home.

The cost of permit drawings can depend on:

  • Project size

  • Project complexity

  • Existing building conditions

  • Site measurements

  • Number of drawings required

  • Design development

  • Structural complexity

  • Zoning constraints

  • Engineering requirements

  • Consultant coordination

  • Revisions

  • Municipal requirements

For that reason, the best way to establish a fee is to review the property and proposed scope of work.

Homeowners should also distinguish between the cost of preparing the drawings and the municipal building permit fee.

Municipalities charge their own application and permit fees separately. Depending on the project, there may also be engineering, surveying, grading, HVAC or other consultant costs.

Do I Need a BCIN Designer?

Ontario regulates certain building designers through the Building Code qualification and registration system.

A BCIN — Building Code Identification Number — is associated with Ontario's system for qualified building practitioners.

Depending on the project and applicable exemptions, permit drawings submitted to a municipality may need to be prepared or reviewed by an appropriately qualified designer, architect or professional engineer.

For many residential projects, working with a qualified designer can provide a practical route from the initial concept through permit drawings and municipal submission.

Do I Need a Structural Engineer?

Not every residential project requires the same amount of structural engineering.

Engineering may be required depending on the proposed construction and structural conditions.

Examples can include certain:

  • Beams

  • Large structural openings

  • Foundation conditions

  • Posts and load paths

  • Structural alterations

  • Unusual framing conditions

Where engineering is required, it should be coordinated with the architectural permit drawings.

That coordination matters.

An architectural drawing showing one structural condition while the engineer's drawing shows something different can create permit comments and confusion during construction.

Building an Addition?

Additions are among the projects where early planning matters most.

Before designing the addition, you should understand:

  1. What zoning permits you to build

  2. What currently exists

  3. How the addition connects to the existing structure

  4. Whether structural engineering will be required

  5. Whether grading, surveying or other consultants will be necessary

Solving those questions early can save considerable time later.

Converting a Basement or Adding Another Dwelling Unit?

Additional dwelling units, basement apartments and residential conversions can involve considerably more than drawing another kitchen and bedroom.

Depending on the project, considerations may include:

  • Fire separations

  • Exits

  • Ceiling heights

  • Natural light

  • Smoke and carbon monoxide alarms

  • HVAC

  • Plumbing

  • Parking and zoning

  • Structural modifications

Existing conditions become particularly important in conversion projects.

A design that works perfectly on paper still needs to work within the constraints of the existing building.

Planning a Deck or Garage?

Decks and garages may appear relatively straightforward, but permit and zoning requirements still need to be considered.

For a deck, this can include:

  • Setbacks

  • Footings

  • Posts

  • Beams

  • Joists

  • Guards

  • Stairs

  • Connections to the existing house

For garages, considerations can include:

  • Property setbacks

  • Building size

  • Height

  • Foundations

  • Structural framing

  • Lot coverage

  • Relationship to the existing house

Checking the property before developing the drawings can prevent a proposed structure from being designed in a location that isn't permitted.

What Makes a Good Permit Drawing Package?

A permit package shouldn't merely contain enough drawings to fill a submission checklist.

The drawings should work together.

Floor plans, elevations, sections, details and engineering should tell the same story.

Dimensions should be coordinated. Existing and proposed construction should be clear. Structural information should correspond with the architectural design.

Ambiguous drawings create questions.

Questions create revisions.

Revisions cost time.

Clear, coordinated drawings help reduce those problems during both permit review and construction.

Building Permit Drawing Services Across Ontario

Max Humenyuk Design provides residential design and building permit drawing services for homeowners, builders and contractors across Ontario.

Projects can include:

  • Home additions

  • Renovations

  • Custom homes

  • Decks and porches

  • Garages

  • Secondary suites

  • Additional dwelling units

  • Duplex and triplex conversions

  • As-built drawings

  • Permit drawings

  • Zoning and feasibility reviews

  • Consultant and engineering coordination

Services are available for projects throughout Orillia, Barrie, Simcoe County, the Greater Toronto Area and other Ontario municipalities.

Need Building Permit Drawings for Your Ontario Project?

If you're considering a renovation, addition, deck, garage, secondary suite, residential conversion or new home, you don't need to have every detail figured out before getting started.

Reviewing the property and proposed scope early can help identify zoning constraints, permit requirements and consultant needs before significant time or money is invested in the design.

Have a project in Ontario? Contact Max Humenyuk Design to discuss your project and get a quote for building permit drawings.